There are a number of cracks in the internal corridor walls of Ben Jonson House which have been around for some time now, some worse than others, for example:

Made worse by a water accident
Here is the latest from a BEO engineer:

I’m currently dealing with various internal cracks at Ben Johnson in all floors with a Structural Engineer and a Specialist Contractor. The Engineer has produced a survey report for the cracks. We met this morning discussing the various options in the report on remedying the problems in order to put together costs. The two flat cracks have been covered by the report and would be part of the works. Although it is internal the works may involve Planners as it is a listed building. My next action is to lead the project team to meet with Planners asap to discuss way forward.